Cass, NE interconnection queue
11 active projects totaling 2,803.7 MW in the SPP queue, plus 12 with terminal status (shown grayed).
11active projects
2,803.7active MW
23total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2020-035 | Not reported | 345 | 424.5 | Gas | Withdrawn |
| GEN-2024-213 | Not reported | 345 | 360 | Gas | Active |
| GEN-2020-036 | Not reported | 345 | 303 | Hybrid | Withdrawn |
| GEN-2020-040 | Not reported | 345 | 303 | Gas | Withdrawn |
| GEN-2024-211 | Not reported | 345 | 303 | Gas | Active |
| GEN-2024-212 | Not reported | 345 | 303 | Gas | Active |
| GEN-2020-038 | Not reported | 345 | 272.7 | Gas | Active |
| GEN-2023-079 | Not reported | 345 | 272.7 | Gas | Active |
| GEN-2023-077 | Not reported | 345 | 255 | Gas | Active |
| GEN-2023-078 | Not reported | 345 | 255 | Gas | Active |
| GEN-2008-121O | Not reported | n/r | 249 | Gas | Withdrawn |
| GEN-2018-033 | Not reported | 345 | 200 | Battery | Suspended |
| GEN-2021-040 | Not reported | 345 | 200 | Battery | Active |
| GEN-2025-SR26 | Not reported | 345 | 200 | Other | Active |
| GEN-2021-108 | Not reported | 345 | 182.3 | Solar | Active |
| GEN-2007-033O | Not reported | n/r | 170 | Gas | Withdrawn |
| GEN-2023-197 | Not reported | 161 | 150 | Solar | Withdrawn |
| GEN-2009-003O1 | Not reported | 161 | 80 | Wind | Withdrawn |
| GEN-2020-037 | Not reported | 345 | 56.5 | Gas | Withdrawn |
| GEN-2020-039 | Not reported | 345 | 56.5 | Gas | Withdrawn |
| GEN-2020-041 | Not reported | 345 | 56.5 | Gas | Withdrawn |
| GEN-2020-042 | Not reported | 345 | 56.5 | Gas | Withdrawn |
| GEN-2019-010 | Not reported | 69 | 50 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.