Powerton substation interconnection queue
2 active projects totalling 300 MW in the PJM queue, plus 3 with terminal status (shown greyed).
2active projects
300active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AG2-363 | Powerton 345 kV | 345 | 180 | Solar | Active |
| AG2-364 | Powerton 345 kV | 345 | 120 | Solar | Active |
| AH1-191 | Powerton 138 kV | 138 | 12.1 | Hybrid | Withdrawn |
| AC1-171 | ZEP Valley Wind Farm | n/r | 10.3 | Wind | Withdrawn |
| W3-046 | Powerton 345kV | 345 | 0 | Wind | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.