Perry substation interconnection queue
2 active projects totaling 229 MW in the PJM queue.
2 PJM queue filings name Perry as the point of interconnection, all in Lake County, OH.
Target commercial operation date as filed: Dec 2031 (1 filing). 1 active filing targets a date after November 27, 2026.
Transmission owner as filed: ATSI (1 filing).
2active projects
229active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| C01-1502 | Perry 345 kV | 345 | 213 | Nuclear | Active | Dec 2031 |
| W4-004B_AT11 | Perry Nuclear Power Plant | 345 | 16 | Nuclear | In Service | n/r |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.