Lake, OH interconnection queue
2 active projects totalling 229 MW in the PJM queue, plus 4 with terminal status (shown greyed).
2active projects
229active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| Y1-035 | Eastlake 138kV | 138 | 462 | Gas | Withdrawn |
| Y1-036 | Eastlake 345kV | 345 | 462 | Gas | Withdrawn |
| C01-1502 | Perry 345 kV | 345 | 213 | Nuclear | Active |
| W4-004B_AT11 | Perry Nuclear Power Plant | 345 | 16 | Nuclear | In Service |
| AC2-099 | Nursery 36kV | 36 | 3 | Gas | Withdrawn |
| AB1-115 | Lake County Generating Station | 13 | 2.5 | Gas | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.