North Hampton substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name North Hampton as the point of interconnection, all in Clark County, OH.
Target commercial operation date as filed: Dec 2028 (2 filings).
Transmission owner as filed: ATSI (2 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG2-385 | North Hampton 69 kV | 69 | 36.5 | Solar | Withdrawn | Dec 2028 |
| AG2-063 | North Hampton 69 kV | 69 | 34.5 | Solar | Withdrawn | Dec 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: North Hampton Substation (ATSI, 2 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Other PJM queue substations in Clark County, OH
- Greene - Madison: none active of 2 filed