Guardian substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Guardian as the point of interconnection, all in Noble County, IN.
Target commercial operation dates as filed run from Dec 2022 to Dec 2023 (2 filings).
Transmission owner as filed: AEP (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG1-453 | Guardian 138 kV | 138 | 84 | Solar | Withdrawn | Dec 2023 |
| AG1-454 | Guardian 138 kV | 138 | 50 | Battery | Withdrawn | Dec 2022 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Noble County, IN
No other substation in Noble County, IN is named as a point of interconnection in the PJM queue.