Rockport Unit #1

PJM queue ID Y3-038

Rockport Unit #1 (Y3-038) is listed in the PJM interconnection queue as a 36 MW coal project in Spencer County, IN. The filing names Rockport Unit 1 as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 30, 2017.

Queue IDY3-038
Project nameRockport Unit #1
Status (as published)In Service
SubstationRockport Unit 1
Point of interconnectionRockport Unit 1
CountySpencer
StateIN
VoltageNot reported
Capacity36 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Target commercial operation2017-06-30
Source datasetserial

Same substation and county

Spencer, IN: 11 requests in the PJM queue, 7 active totaling 9,176 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy36
MW capacity36
MFO1356

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.