Gavin Unit #2 (Y3-036) is listed in the PJM interconnection queue as a 36 MW coal project in Gallia County, OH. The filing names Gavin Unit 2 as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2014.

Queue IDY3-036
Project nameGavin Unit #2
Status (as published)In Service
SubstationGavin Unit 2
Point of interconnectionGavin Unit 2
CountyGallia
StateOH
VoltageNot reported
Capacity36 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Target commercial operation2014-12-31
Source datasetserial

Same substation and county

Gallia, OH: 6 requests in the PJM queue, 5 active totaling 87 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy36
MW capacity36
MFO1356

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first