Substation Scout

Rochelle Plant

PJM queue ID Y1-054

Rochelle Plant (Y1-054) is listed in the PJM interconnection queue as a gas request filed at 0 MW (a net change or energy-only filing) in Hamilton County, OH. The filing names Rochelle as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of May 1, 2013.

Queue IDY1-054
Project nameRochelle Plant
Status (as published)In Service
SubstationRochelle
Point of interconnectionRochelle 138kV
CountyHamilton
StateOH
Voltage138 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2013-05-01
Source datasetserial

Same substation and county

Rochelle substation: 3 requests in the PJM queue, 3 active totaling 22 MW.

Queue IDProjectMWResourceStatus
M21City of Rochelle, IL20OtherIn Service
O05City of Rochelle2OtherIn Service

Hamilton, OH: 7 requests in the PJM queue, 4 active totaling 227 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy20
MW capacity0
MFO20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.