Substation Scout

Willow Island Hydro Generation Project

PJM queue ID Y1-044

Willow Island Hydro Generation Project (Y1-044) is listed in the PJM interconnection queue as a 6.8 MW hydro project in Pleasants County, WV. The filing names Belmont as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of July 31, 2015.

Queue IDY1-044
Project nameWillow Island Hydro Generation Project
Status (as published)In Service
SubstationBelmont
Point of interconnectionBelmont 138kV
CountyPleasants
StateWV
Voltage138 kV
Capacity6.8 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Target commercial operation2015-07-31
Source datasetserial

Same substation and county

Belmont substation: 2 requests in the PJM queue, 2 active totaling 14.4 MW.

Queue IDProjectMWResourceStatus
C01-1744Belmont 230 kV7.6GasActive

Pleasants, WV: 6 requests in the PJM queue, 5 active totaling 392.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy6.8
MW capacity6.8
MFO43.2

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first