MEC-PJM
PJM queue ID W1-017 1325402
MEC-PJM (W1-017 1325402) is listed in the PJM interconnection queue as a long-term firm transmission request for 50 MW. PJM lists its status as “Confirmed”.
| Queue ID | W1-017 1325402 |
|---|---|
| Project name | MEC-PJM |
| Status (as published) | Confirmed |
| Substation | MEC-PJM |
| Point of interconnection | MEC-PJM |
| County | Not reported |
| State | Not reported |
| Voltage | Not reported |
| Capacity | 50 MW |
| Resource (as published) | Not reported |
| Resource category | Not reported (normalized for filtering) |
| Target commercial operation | Not reported |
| Source dataset | serial |
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Long-Term Firm Transmission |
|---|---|
| MFO | 50 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.