Substation Scout

King - Queen

PJM queue ID Q69

King - Queen (Q69) is listed in the PJM interconnection queue as a 10 MW gas project in Brunswick County, VA. The filing names Shackleford as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of February 7, 2008.

Queue IDQ69
Project nameKing - Queen
Status (as published)In Service
SubstationShackleford
Point of interconnectionShackleford 34.5kV
CountyBrunswick
StateVA
Voltage34.5 kV
Capacity10 MW
Resource (as published)Methane
Resource categoryGas (normalized for filtering)
Target commercial operation2008-02-07
Source datasetserial

Same substation and county

Shackleford substation: 3 requests in the PJM queue, 2 active totaling 12.2 MW.

Queue IDProjectMWResourceStatus
AC1-063King & Queen Landfill Facility2.2GasIn Service
O62Shackleford 34.5kV8GasWithdrawn

Brunswick, VA: 45 requests in the PJM queue, 18 active totaling 2,685.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy10
MW capacity10
MFO10

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.