Easton Utilities Substation 2
PJM queue ID K07
Easton Utilities Substation 2 (K07) is listed in the PJM interconnection queue as a 5 MW gas project in Talbot County, MD. The filing names Easton as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of November 1, 2004.
| Queue ID | K07 |
|---|---|
| Project name | Easton Utilities Substation 2 |
| Status (as published) | In Service |
| Substation | Easton |
| Point of interconnection | Easton 69kV |
| County | Talbot |
| State | MD |
| Voltage | 69 kV |
| Capacity | 5 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2004-11-01 |
| Source dataset | serial |
Same substation and county
Easton substation: 2 requests in the PJM queue, 2 active totaling 10 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| K06 | Easton Utilities Substation 2 | 5 | Gas | In Service |
Talbot, MD: 16 requests in the PJM queue, 6 active totaling 269.8 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 5 |
| MW capacity | 5 |
| MFO | 10 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.