W. Millersport 345 kV

PJM queue ID C01-2246

W. Millersport 345 kV (C01-2246) is listed in the PJM interconnection queue as a gas request filed at 0 MW (a net change or energy-only filing) in Fairfield County, OH. The filing names W. Millersport as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of April 1, 2029.

Queue IDC01-2246
Project nameW. Millersport 345 kV
Status (as published)Active
SubstationW. Millersport
Point of interconnectionW. Millersport 345 kV
CountyFairfield
StateOH
Voltage345 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2029-04-01
Source datasetcycle

Same substation and county

Fairfield, OH: 10 requests in the PJM queue, 5 active totaling 607.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperAnchor Power and Energy Solutions, LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy1300.0
MW capacity0.0
MFO1300.0
Submitted date4/27/2026
Last updated6/17/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first