West Landing 230 kV
PJM queue ID C01-2101
West Landing 230 kV (C01-2101) is listed in the PJM interconnection queue as a 300 MW battery project in Chesapeake County, VA. The filing names West Landing as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of March 14, 2031.
| Queue ID | C01-2101 |
|---|---|
| Project name | West Landing 230 kV |
| Status (as published) | Active |
| Substation | West Landing |
| Point of interconnection | West Landing 230 kV |
| County | Chesapeake |
| State | VA |
| Voltage | 230 kV |
| Capacity | 300 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2031-03-14 |
| Source dataset | cycle |
Same substation and county
Chesapeake, VA: 5 requests in the PJM queue, 5 active totaling 995 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Bayberry Energy, LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 300.0 |
| MW capacity | 300.0 |
| MFO | 300.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/23/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.