Junction City 138 kV (C01-2024) is listed in the PJM interconnection queue as a 250 MW gas project in Perry County, OH. The filing names Junction City as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of May 31, 2031.
| Queue ID | C01-2024 |
|---|---|
| Project name | Junction City 138 kV |
| Status (as published) | Active |
| Substation | Junction City |
| Point of interconnection | Junction City 138 kV |
| County | Perry |
| State | OH |
| Voltage | 138 kV |
| Capacity | 250 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2031-05-31 |
| Source dataset | cycle |
Same substation and county
Perry, OH: 9 requests in the PJM queue, 4 active totaling 2,118.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Cortex Sycamore, LLC |
|---|---|
| Transmission owner | AEP |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 250.0 |
| MW capacity | 250.0 |
| MFO | 250.0 |
| Submitted date | 4/25/2026 |
| Last updated | 6/25/2026 |