Erie West - Wayne 345 kV
PJM queue ID C01-2015
Erie West - Wayne 345 kV (C01-2015) is listed in the PJM interconnection queue as a 200 MW battery project in Crawford County, PA. The filing names Erie West - Wayne as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of May 1, 2031.
| Queue ID | C01-2015 |
|---|---|
| Project name | Erie West - Wayne 345 kV |
| Status (as published) | Active |
| Substation | Erie West - Wayne |
| Point of interconnection | Erie West - Wayne 345 kV |
| County | Crawford |
| State | PA |
| Voltage | 345 kV |
| Capacity | 200 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2031-05-01 |
| Source dataset | cycle |
Same substation and county
Crawford, PA: 56 requests in the PJM queue, 9 active totaling 915.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Lightsource Renewable Energy Development, LLC |
|---|---|
| Transmission owner | PENELEC |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 200.0 |
| MW capacity | 200.0 |
| MFO | 200.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/8/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.