Chestnut - Blue Mound 345 kV
PJM queue ID C01-1870
Chestnut - Blue Mound 345 kV (C01-1870) is listed in the PJM interconnection queue as a 331 MW wind project in McLean County, IL. The filing names Chestnut - Blue Mound as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of April 15, 2031.
| Queue ID | C01-1870 |
|---|---|
| Project name | Chestnut - Blue Mound 345 kV |
| Status (as published) | Active |
| Substation | Chestnut - Blue Mound |
| Point of interconnection | Chestnut - Blue Mound 345 kV |
| County | McLean |
| State | IL |
| Voltage | 345 kV |
| Capacity | 331 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2031-04-15 |
| Source dataset | cycle |
Same substation and county
McLean, IL: 41 requests in the PJM queue, 15 active totaling 1,021.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Emerald Wind, LLC |
|---|---|
| Transmission owner | ComEd |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 500.0 |
| MW capacity | 331.0 |
| MFO | 500.0 |
| Submitted date | 4/27/2026 |
| Last updated | 10/8/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.