Substation Scout

AE2-045 TAP 345 kV

PJM queue ID C01-1634

Queue IDC01-1634
Project nameAE2-045 TAP 345 kV
Status (as published)Active
SubstationAE2-045 TAP
Point of interconnectionAE2-045 TAP 345 kV
CountyPulaski
StateIN
Voltage345 kV
Capacity48 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2028-04-24
Source datasetcycle

Additional filed fields

DeveloperBottlebrush Solar Energy LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy0.0
Mw Capacity47.98
Mfo275.0
Submitted Date4/25/2026
Last Updated6/15/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.