Substation Scout

Venango Junction - Edinboro South 115 kV

PJM queue ID C01-1081

Queue IDC01-1081
Project nameVenango Junction - Edinboro South 115 kV
Status (as published)Active
SubstationVenango Junction - Edinboro South
Point of interconnectionVenango Junction - Edinboro South 115 kV
CountyCrawford
StatePA
Voltage115 kV
Capacity116.5 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2032-05-03
Source datasetcycle

Additional filed fields

DeveloperLightsource Renewable Energy Development, LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy116.5
Mw Capacity116.5
Mfo116.5
Submitted Date4/27/2026
Last Updated5/28/2026