Rankin - Wilmerding 23 kV (C01-1031) is listed in the PJM interconnection queue as a 5.3 MW hydro project in Allegheny County, PA. The filing names Rankin - Wilmerding as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2026.

Queue IDC01-1031
Project nameRankin - Wilmerding 23 kV
Status (as published)Active
SubstationRankin - Wilmerding
Point of interconnectionRankin - Wilmerding 23 kV
CountyAllegheny
StatePA
Voltage23 kV
Capacity5.3 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Target commercial operation2026-12-31
Source datasetcycle

Same substation and county

Allegheny, PA: 64 requests in the PJM queue, 11 active totaling 1,589.8 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperLock+ Hydro Friends Fund XLII, LLC
Transmission ownerDL
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy5.25
MW capacity5.25
MFO5.25
Submitted date10/29/2025
Last updated6/25/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first