Substation Scout

Ford Mill

PJM queue ID B30

Queue IDB30
Project nameFord Mill
Status (as published)In Service
SubstationEmilie
Point of interconnectionEmilie 230kV
CountyBucks
StatePA
Voltage230 kV
Capacity1,145 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2004-06-29
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1268
Mw Capacity1145
Mfo1268

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.