Substation Scout

Red Onion - VC5 69 kV

PJM queue ID AH1-073

Red Onion - VC5 69 kV (AH1-073) is listed in the PJM interconnection queue as a 12 MW solar project in Dickenson County, VA. The filing names Red Onion - VC5 as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 1, 2028.

Queue IDAH1-073
Project nameRed Onion - VC5 69 kV
Status (as published)Active
SubstationRed Onion - VC5
Point of interconnectionRed Onion - VC5 69 kV
CountyDickenson
StateVA
Voltage69 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2028-12-01
Source datasetcycle

Same substation and county

Red Onion - VC5 substation: 2 requests in the PJM queue, 2 active totaling 24 MW.

Queue IDProjectMWResourceStatus
AH1-072Red Onion - VC5 69 kV12SolarActive

Dickenson, VA: 2 requests in the PJM queue, 2 active totaling 24 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperBold Camp CF Solar, LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleTC2
StagePhase 3
MW energy20.0
MW capacity12.0
MFO40.0
Submitted date7/29/2021
Last updated8/25/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first