Substation Scout

Cass County Solar

PJM queue ID AF2-396

Cass County Solar (AF2-396) is listed in the PJM interconnection queue as a 200 MW hybrid project in Cass County, MI. The filing names Stinger as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of June 1, 2029.

Queue IDAF2-396
Project nameCass County Solar
Status (as published)EP
SubstationStinger
Point of interconnectionStinger 138 kV
CountyCass
StateMI
Voltage138 kV
Capacity200 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalized for filtering)
Target commercial operation2029-06-01
Source datasetcycle

Same substation and county

Cass, MI: 20 requests in the PJM queue, 7 active totaling 1,778.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperSteelhead Solar, LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
MW energy200.0
MW capacity200.0
MFO200.0
Submitted date3/31/2020
Last updated2/23/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first