Substation Scout

Washington Solar PH II

PJM queue ID AF2-354

Washington Solar PH II (AF2-354) is listed in the PJM interconnection queue as a 4.6 MW solar project in Warren County, NJ. The filing names Washington II as its point of interconnection. PJM lists its status as “Partially in Service - Under Construction”, with a target commercial operation date of September 1, 2026.

Queue IDAF2-354
Project nameWashington Solar PH II
Status (as published)Partially in Service - Under Construction
SubstationWashington II
Point of interconnectionWashington 34.5 kV II
CountyWarren
StateNJ
Voltage34.5 kV
Capacity4.6 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2026-09-01
Source datasetserial

Same substation and county

Warren, NJ: 113 requests in the PJM queue, 24 active totaling 353.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy11
MW capacity4.62
MFO19.8

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.