Substation Scout

Courthouse Solar

PJM queue ID AF2-222

Queue IDAF2-222
Project nameCourthouse Solar
Status (as published)EP
SubstationMadisonville DP-Twitty's Creek
Point of interconnectionMadisonville DP-Twitty's Creek 115 kV
CountyCharlotte
StateVA
Voltage115 kV
Capacity100 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2031-03-01
Source datasetcycle

Additional filed fields

DeveloperVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy167.0
Mw Capacity100.0
Mfo167.0
Submitted Date3/25/2020
Last Updated8/19/2026