Substation Scout

Lyons Solar

PJM queue ID AD2-115

Lyons Solar (AD2-115) is listed in the PJM interconnection queue as a 13 MW solar project in Berks County, PA. The filing names Lyons-Moselem as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of August 31, 2023.

Queue IDAD2-115
Project nameLyons Solar
Status (as published)In Service
SubstationLyons-Moselem
Point of interconnectionLyons-Moselem 69kV
CountyBerks
StatePA
Voltage69 kV
Capacity13 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2023-08-31
Source datasetserial

Same substation and county

Berks, PA: 63 requests in the PJM queue, 12 active totaling 1,177.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy20
MW capacity13
MFO20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner