Riverstart Solar Park IV
PJM queue ID AD1-128
Riverstart Solar Park IV (AD1-128) is listed in the PJM interconnection queue as a 57 MW solar project in Randolph County, IN. The filing names Modoc-Delaware as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2025.
| Queue ID | AD1-128 |
|---|---|
| Project name | Riverstart Solar Park IV |
| Status (as published) | In Service |
| Substation | Modoc-Delaware |
| Point of interconnection | Modoc-Delaware 138 kV |
| County | Randolph |
| State | IN |
| Voltage | 138 kV |
| Capacity | 57 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2025-12-31 |
| Source dataset | serial |
Same substation and county
Randolph, IN: 43 requests in the PJM queue, 17 active totaling 939 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 150 |
| MW capacity | 57 |
| MFO | 150 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.