Substation Scout

Gardy's Mill Solar

PJM queue ID AC2-138

Gardy's Mill Solar (AC2-138) is listed in the PJM interconnection queue as a 4.8 MW solar project in Westmoreland County, VA. The filing names Northern Neck as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 30, 2020.

Queue IDAC2-138
Project nameGardy's Mill Solar
Status (as published)In Service
SubstationNorthern Neck
Point of interconnectionNorthern Neck 34.5kV
CountyWestmoreland
StateVA
Voltage34.5 kV
Capacity4.8 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2020-12-30
Source datasetserial

Same substation and county

Northern Neck substation: 6 requests in the PJM queue, 3 active totaling 8.4 MW.

Queue IDProjectMWResourceStatus
AF1-248Gardy’s Mill Solar2.1SolarIn Service
AD2-044Gardy's Mill Solar1.5SolarIn Service
AH1-134Northern Neck 230 kV12BatteryWithdrawn
AG1-256Northern Neck 230 kV8BatteryWithdrawn
AG1-210Haynesville Energy Storage4BatteryWithdrawn

Westmoreland, VA: 20 requests in the PJM queue, 8 active totaling 264.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy10.8
MW capacity4.8
MFO10.8

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.