Piney Station (Piney 1-3)

PJM queue ID AA1-037

Piney Station (Piney 1-3) (AA1-037) is listed in the PJM interconnection queue as a 5.3 MW hydro project in Clarion County, PA. The filing names Piney Hydro as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2015.

Queue IDAA1-037
Project namePiney Station (Piney 1-3)
Status (as published)In Service
SubstationPiney Hydro
Point of interconnectionPiney Hydro 34.5kV
CountyClarion
StatePA
Voltage34.5 kV
Capacity5.3 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Target commercial operation2015-06-01
Source datasetserial

Same substation and county

Clarion, PA: 25 requests in the PJM queue, 7 active totaling 320.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy5.26
MW capacity5.26
MFO33.26

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first