3 active projects totalling 255 MW in the PJM queue, plus 8 with terminal status (shown greyed).

3active projects
255active MW
11total filed
Queue IDProjectkVMWResourceStatus
C01-1691 South Berwick - Fostoria CTL 345 kV 345 150 Gas Active
AG2-289 Amsden - Fremont Center 69 kV 69 66.6 Battery Active
AD2-136 Melmore Tap 138kV 138 46.8 Wind Withdrawn
AG2-290 Amsden - Fremont Center 69 kV 69 38.4 Battery Active
AE2-174 Fremont Center-Tiffin Center 138 kV circuit #1 138 34.9 Wind Withdrawn
AI1-091 Bascom 69 kV 69 31.5 Solar Withdrawn
AG2-465 South Tiffin - West End Fostoria 138 kV 138 29.4 Hybrid Withdrawn
V4-010 Republic Wind LLC 138 26 Wind Withdrawn
AD2-191 Melmore 138kV 138 22.1 Wind Withdrawn
U4-028 Seneca Wind 138 13 Wind Withdrawn
U4-029 Seneca Wind 138 13 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.