Nicholas, WV interconnection queue
2 active projects totalling 137.7 MW in the PJM queue, plus 5 with terminal status (shown greyed).
2active projects
137.7active MW
7total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AG2-686 | Powell Mountain 138 kV | 138 | 129 | Solar | Withdrawn |
| AF2-316 | Deep Lake Solar | 138 | 82.7 | Solar | Engineering and Procurement |
| AG2-314 | Gilboa-Jones Branch 138 kV III | 138 | 67 | Battery | Withdrawn |
| AF2-311 | Nicholas Solar | 138 | 55 | Solar | Engineering and Procurement |
| AI2-332 | Gilboa-Jones Branch 138 kV VI | 138 | 40 | Solar | Withdrawn |
| AH1-426A | Gilboa-Jones Branch 138 kV V | 138 | 32.3 | Battery | Withdrawn |
| AI2-339 | Gilboa-Jones Branch 138 kV VII | 138 | 26.8 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.