Nicholas, WV interconnection queue

2 active projects totalling 137.7 MW in the PJM queue, plus 5 with terminal status (shown greyed).

2active projects
137.7active MW
7total filed
Queue IDProjectkVMWResourceStatus
AG2-686 Powell Mountain 138 kV 138 129 Solar Withdrawn
AF2-316 Deep Lake Solar 138 82.7 Solar Engineering and Procurement
AG2-314 Gilboa-Jones Branch 138 kV III 138 67 Battery Withdrawn
AF2-311 Nicholas Solar 138 55 Solar Engineering and Procurement
AI2-332 Gilboa-Jones Branch 138 kV VI 138 40 Solar Withdrawn
AH1-426A Gilboa-Jones Branch 138 kV V 138 32.3 Battery Withdrawn
AI2-339 Gilboa-Jones Branch 138 kV VII 138 26.8 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.