Lucas, OH interconnection queue
3 active projects totalling 940.8 MW in the PJM queue, plus 8 with terminal status (shown greyed).
3active projects
940.8active MW
11total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AH1-690 | Bay Shore - Lallendorf 345 kV | 345 | 1,440 | Gas | Withdrawn |
| AB1-107 | Cedar Point Energy Center | 138 | 860 | Gas | Withdrawn |
| Y1-069 | Oregon Energy Center | 345 | 799 | Gas | In Service |
| Z1-030 | Bay Shore 138kV | 138 | 464 | Gas | Withdrawn |
| AG1-199 | Allen Junction 345 kV | 345 | 300 | Battery | Withdrawn |
| U2-028A_AT1 | FDS Coke Plant | n/r | 135 | Other | Withdrawn |
| AG2-223 | Allen Junction 345 kV | 345 | 100 | Battery | Withdrawn |
| C01-1948 | Bay Shore 138 kV | 138 | 95.8 | Gas | Active |
| AG2-515 | Midway 345 kV III | 345 | 60 | Solar | Withdrawn |
| AA1-056 | Oregon Energy Center | 345 | 46 | Gas | In Service |
| Y2-091 | Toledo Solar | n/r | 0 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.