Green, KY interconnection queue
3 active projects totalling 177 MW in the PJM queue, plus 3 with terminal status (shown greyed).
3active projects
177active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AH1-751 | Not reported | n/r | 150 | Battery | Withdrawn |
| AG1-354 | Exie Solar | 161 | 90 | Solar | EP |
| C01-1216 | Magnolia - Summersville 69 kV | 69 | 51 | Solar | Active |
| AI1-165 | Magnolia - Summersville 69 kV | 69 | 50 | Hybrid | Withdrawn |
| AG2-670 | Greensburg 69 kV | 69 | 45 | Solar | Withdrawn |
| AF1-050 | Horseshoe Bend Solar | 161 | 36 | Solar | Under Construction |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.