Elkhart, IN interconnection queue
2 active projects totalling 71.9 MW in the PJM queue, plus 6 with terminal status (shown greyed).
2active projects
71.9active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AE2-332 | Twin Branch-Guardian 138 kV | 138 | 208.8 | Battery | Withdrawn |
| AG2-332 | East Elkhart - Elcona Tap 138 kV | 138 | 100 | Battery | Withdrawn |
| AG1-222 | Guardian-Twin Branch 138 kV | 138 | 90 | Battery | Withdrawn |
| AE2-323 | Elkhart County Solar Project | 138 | 67.1 | Solar | In Service |
| AG2-315 | Twin Branch - Guardian 138 kV | 138 | 60 | Battery | Withdrawn |
| AF1-046 | Twin Branch-Guardian 138 kV | 138 | 31.3 | Battery | Withdrawn |
| Y3-023 | Wabash Valley Power Association, Inc. | 12 | 4.8 | Gas | In Service |
| AG2-248 | East Elkhart - Elcona Tap 138 kV | 138 | 0 | Battery | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.