Elk, PA interconnection queue
2 active projects totalling 93 MW in the PJM queue, plus 12 with terminal status (shown greyed).
2active projects
93active MW
14total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| H24 | Forest 230kV | 230 | 575 | Gas | Withdrawn |
| C01-1165 | Ridgeway - Elko 138 kV | 138 | 250 | Hybrid | Withdrawn |
| B44 | Elko-Forrest 230kV | 230 | 240 | Gas | Withdrawn |
| AI1-213 | Farmers Valley - Ridgeway 115 kV VI | 115 | 174 | Hybrid | Withdrawn |
| AI1-040 | Ridgway - Elko 138 kV | 138 | 150 | Solar | Withdrawn |
| AE2-177 | Squabb SVC 230 kV | 230 | 99 | Solar | Withdrawn |
| AF1-220 | Ridgway-Whetstone 115 kV | 115 | 91 | Solar | Withdrawn |
| C01-1225 | Elko - Shawville 230 kV | 230 | 81 | Wind | Active |
| AF1-306 | Squab Hollow 230 kV | 230 | 49.3 | Battery | Withdrawn |
| W4-012 | Whetstone 115kV | 115 | 15.6 | Wind | Withdrawn |
| AG2-538 | Ridgeway - Motion Control 46 kV | 46 | 15.4 | Hybrid | Withdrawn |
| AF1-153 | Jakes Hollow Solar | 46 | 12 | Solar | Suspended |
| AF1-155 | EL-Mefferts Run | 46 | 12 | Solar | Withdrawn |
| AF2-295 | Evergreen Solar | 46 | 12 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.