Barbour, WV interconnection queue

4 active projects totalling 196.2 MW in the PJM queue, plus 6 with terminal status (shown greyed).

4active projects
196.2active MW
10total filed
Queue IDProjectkVMWResourceStatus
AH1-252 Wharton - Sundial 138 kV 138 100 Battery Withdrawn
C01-1380 Leadsville 138 kV 138 100 Battery Active
AG2-423 Cherry Run - Harmony 138 kV 138 48 Solar Active
AH1-254 Mount Storm Repower 500 36.5 Wind Active
AG2-011 Laurel Mountain 138 kV 138 34.2 Battery Withdrawn
U4-017 Corder Crossing 138kV 138 21.5 Wind Withdrawn
V2-026 Denver 138kV 138 21.3 Wind Withdrawn
P59 Laurel Mountain WF 138 11.7 Wind In Service
AC1-073 Laurel Mountain Wind Farm & Energy Storage Facility 138 5.8 Hybrid Canceled
W2-057 Laurel Mountain BT n/r 0 Battery Deactivated

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.