MISO request J4195

MISO queue ID J4195

Queue request J4195 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW wind project in Clinton County, MI, according to Berkeley Lab’s queue data file. The filing names GREENWOOD - RAPSON as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 2, 2030.

Queue IDJ4195
Project nameNot reported
Status (as published)Active
SubstationGREENWOOD - RAPSON
Point of interconnectionGREENWOOD - RAPSON 345.0kV
CountyClinton
StateMI
Voltage345 kV
Capacity300 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2030-04-02
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

GREENWOOD - RAPSON substation: 5 requests in the MISO queue, 5 active totaling 1,170 MW.

Queue IDProjectMWResourceStatus
J3977Not reported250BatteryActive
J3496Not reported220WindActive
J2667Not reported200SolarActive
J2878Not reported200SolarActive

Clinton, MI: 8 requests in the MISO queue, 2 active totaling 450 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP Cycle Pending East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-09

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.