GREENWOOD - RAPSON substation interconnection queue

5 active projects totaling 1,170 MW in the MISO queue.

5 MISO queue filings name GREENWOOD - RAPSON as the point of interconnection, all in MI.

5active projects
1,170active MW
5total filed
Queue IDProjectkVMWResourceStatus
J4195 Not reported 345 300 Wind Active
J3977 Not reported 345 250 Battery Active
J3496 Not reported 345 220 Wind Active
J2667 Not reported 345 200 Solar Active
J2878 Not reported 345 200 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.