Substation Scout

MISO request J3977

MISO queue ID J3977

Queue request J3977 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW battery project in Sanilac County, MI, according to Berkeley Lab’s queue data file. The filing names GREENWOOD - RAPSON as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2029.

Queue IDJ3977
Project nameNot reported
Status (as published)Active
SubstationGREENWOOD - RAPSON
Point of interconnectionGREENWOOD - RAPSON 345.0kV
CountySanilac
StateMI
Voltage345 kV
Capacity250 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2029-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

GREENWOOD - RAPSON substation: 5 requests in the MISO queue, 5 active totaling 1,170 MW.

Queue IDProjectMWResourceStatus
J4195Not reported300WindActive
J3496Not reported220WindActive
J2667Not reported200SolarActive
J2878Not reported200SolarActive

Sanilac, MI: 23 requests in the MISO queue, 11 active totaling 2,361.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC
ClusterDPP Cycle Pending East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-03-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.