Substation Scout

MISO request J4126

MISO queue ID J4126

Queue request J4126 was listed in the MISO interconnection queue at the end of 2025 as a 112 MW wind project in Lenawee County, MI, according to Berkeley Lab’s queue data file. The filing names MOROCCO - ALLEN JUNCTION as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 30, 2030.

Queue IDJ4126
Project nameNot reported
Status (as published)Active
SubstationMOROCCO - ALLEN JUNCTION
Point of interconnectionMOROCCO - ALLEN JUNCTION 345.0kV
CountyLenawee
StateMI
Voltage345 kV
Capacity112 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2030-10-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

MOROCCO - ALLEN JUNCTION substation: 2 requests in the MISO queue, 2 active totaling 375 MW.

Queue IDProjectMWResourceStatus
J3313Not reported263WindActive

Lenawee, MI: 22 requests in the MISO queue, 13 active totaling 2,085 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMETC
ClusterDPP Cycle Pending East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-09-16

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first