Substation Scout

MOROCCO - ALLEN JUNCTION substation interconnection queue

2 active projects totaling 375 MW in the MISO queue.

2 MISO queue filings name MOROCCO - ALLEN JUNCTION as the point of interconnection, all in Lenawee County, MI.

2active projects
375active MW
2total filed
Queue IDProjectkVMWResourceStatus
J3313 Not reported 345 263 Wind Active
J4126 Not reported 345 112 Wind Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first