Wayne, MI interconnection queue

12 active projects totaling 2,589.5 MW in the MISO queue, plus 11 with terminal status (shown grayed).

12active projects
2,589.5active MW
23total filed
Queue IDProjectkVMWResourceStatus
G023 Not reported n/r 710 Gas Operational
G095 Not reported n/r 644 Gas Withdrawn
G106 Not reported n/r 520 Gas Withdrawn
J1346 Not reported 345 382 Gas Withdrawn
G038 Not reported n/r 360 Gas Operational
J3872 Not reported n/r 350 Battery Active
G026 Not reported n/r 240 Gas Operational
J444 Not reported 230 235 Gas Withdrawn
R1041 Replacing 220 MW of coal generation with BESS; Trenton Channel 9 120 220 Hybrid Active
J1900 Not reported 120 200 Battery Active
J1902 Not reported n/r 200 Battery Active
J2991 Not reported 120 200 Battery Active
J423 Not reported n/r 125 Gas Withdrawn
J424 Not reported n/r 120 Gas Withdrawn
J2788 Not reported 120 100 Battery Withdrawn
J440 Not reported 230 52 Gas Operational
J471 Not reported 120 50 Solar Withdrawn
G105 Not reported n/r 40 Coal Withdrawn
J1262 Not reported 120 25 Gas Active
J1798 Not reported 120 25 Gas Active
J206 Not reported 120 25 Solar Withdrawn
J149 Not reported 120 13.6 Other Withdrawn
J3763 Not reported n/r 7.5 Other Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.