Substation Scout

St. Charles Parish, LA interconnection queue

4 active projects totaling 1,677.3 MW in the MISO queue, plus 3 with terminal status (shown grayed).

4active projects
1,677.3active MW
7total filed
Queue IDProjectkVMWResourceStatus
J396 Not reported n/r 1,020 Gas Operational
J425 Not reported 230 999 Gas Withdrawn
J3871 Not reported n/r 770 Gas Withdrawn
E0029 Waterford 5 500 478 Gas Active
J1079 Not reported 230 200 Solar Withdrawn
J3815 Not reported n/r 153.1 Nuclear Active
J482 Not reported n/r 26.2 Gas Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first