Substation Scout

Saginaw, MI interconnection queue

12 active projects totaling 2,045.3 MW in the MISO queue, plus 9 with terminal status (shown grayed).

12active projects
2,045.3active MW
21total filed
Queue IDProjectkVMWResourceStatus
G210 CONS 103 Not reported n/r 875 Other Withdrawn
J841 Not reported 138 725 Gas Withdrawn
G207 CONS 37 Not reported n/r 560 Other Withdrawn
G194 CONS 7 Not reported n/r 300 Other Withdrawn
J3843 Not reported 345 300 Solar Active
J3438 Not reported n/r 250 Battery Active
J3656 Not reported n/r 250 Battery Active
J3769 Not reported 345 250 Hybrid Withdrawn
J2061 Not reported n/r 200 Solar Active
J2934 Not reported 345 200 Solar Withdrawn
J2935 Not reported 345 200 Solar Withdrawn
J2813 Not reported 345 195 Solar Withdrawn
J3782 Not reported n/r 180 Battery Active
J4054 Not reported 138 146 Wind Active
J3835 Not reported n/r 130 Solar Active
J1939 Not reported 138 125 Solar Active
J1389 Not reported 345 120 Solar Active
J3124 Not reported 345 120 Solar Active
J3133 Not reported 345 120 Battery Active
E0004 Not reported 138 104.3 Battery Active
J3816 Not reported 138 100 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.