MISO request J1389

MISO queue ID J1389

Queue request J1389 was listed in the MISO interconnection queue at the end of 2025 as a 120 MW solar project in Saginaw County, MI, according to Berkeley Lab’s queue data file. The filing names Murphy Station - Nelson Road Line tap as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2025.

Queue IDJ1389
Project nameNot reported
Status (as published)Active
SubstationMurphy Station - Nelson Road Line tap
Point of interconnectionMurphy Station - Nelson Road 345 kV Line tap
CountySaginaw
StateMI
Voltage345 kV
Capacity120 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2025-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Saginaw, MI: 21 requests in the MISO queue, 12 active totaling 2,045.3 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMETC
ClusterDPP-2019 East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA Complete; Post GIA Status: Not Started
Queue date2019-04-29
Interconnection agreement date2024-07-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.