Substation Scout

Rock Island, IL interconnection queue

5 active projects totaling 1,008 MW in the MISO queue, plus 2 with terminal status (shown grayed).

5active projects
1,008active MW
7total filed
Queue IDProjectkVMWResourceStatus
J372 Not reported n/r 1,373 Nuclear Withdrawn
J3525 Not reported n/r 300 Battery Active
J4112 Not reported 345 300 Wind Active
J3660 Not reported 161 200 Battery Active
J2738 Not reported n/r 128 Hybrid Active
J2552 Not reported 345 80 Battery Active
J1420 Not reported 69 48 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.