Pike, IN interconnection queue
8 active projects totaling 993 MW in the MISO queue, plus 11 with terminal status (shown grayed).
8active projects
993active MW
19total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| G011 | Not reported | n/r | 900 | Gas | Withdrawn |
| J2164 | Not reported | 345 | 250 | Solar | Withdrawn |
| J2507 | Not reported | 345 | 250 | Solar | Withdrawn |
| R1011 | Replace 250MW of the existing Petersburg coal unit with PV and DC-coupled battery storage; Petersburg 2 | 345 | 250 | Hybrid | Active |
| J3997 | Not reported | 345 | 200 | Solar | Withdrawn |
| J3877 | Not reported | n/r | 160 | Solar | Withdrawn |
| J1027 | Not reported | 161 | 150 | Solar | Active |
| J1028 | Not reported | 161 | 150 | Solar | Active |
| J1396 | Not reported | 161 | 150 | Solar | Operational |
| J1398 | Not reported | 161 | 150 | Solar | Withdrawn |
| J1393 | Not reported | 138 | 130 | Solar | Active |
| J3327 | Not reported | 69 | 130 | Battery | Withdrawn |
| S1112 | Not reported | 69 | 130 | Battery | Active |
| J2254 | Not reported | 345 | 100 | Battery | Withdrawn |
| J2514 | Not reported | 345 | 100 | Battery | Withdrawn |
| J3356 | Not reported | 69 | 65 | Hybrid | Withdrawn |
| J1233 | Not reported | 138 | 32.5 | Battery | Withdrawn |
| G646 | Not reported | n/r | 30 | Coal | Operational |
| S1022 | Surplus; Petersburg | 14 | 3 | Hybrid | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.