Linn, IA interconnection queue
16 active projects totaling 3,679.9 MW in the MISO queue, plus 10 with terminal status (shown grayed).
16active projects
3,679.9active MW
26total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| E0025 | Not reported | 345 | 986.9 | Gas | Withdrawn |
| E0050 | Not reported | 345 | 986.9 | Gas | Active |
| E0009 | Linn County Generating Facility | 161 | 675.5 | Nuclear | Withdrawn |
| J3932 | Not reported | 161 | 646 | Nuclear | Active |
| R1012 | Replace 15 MW of ALTW.FPL_DAEC Unit with Battery; Duane Arnold | 161 | 640 | Hybrid | Withdrawn |
| G157 | Not reported | n/r | 500 | Other | Withdrawn |
| G158 | Not reported | n/r | 500 | Other | Withdrawn |
| J2268 | Not reported | n/r | 400 | Solar | Active |
| J2469 | Not reported | 345 | 300 | Battery | Active |
| R5071 | Replacing 244 MW of Solar with Nuclear; Duane Arnold | n/r | 251 | Nuclear | Active |
| J1284 | Not reported | 345 | 250 | Solar | Withdrawn |
| J1444 | Not reported | 345 | 200 | Solar | Active |
| R5069 | Replacing 200 MW of Solar with Nuclear; J1444 | n/r | 200 | Nuclear | Active |
| J4155 | Not reported | 115 | 195 | Battery | Active |
| J2120 | Not reported | n/r | 100 | Battery | Active |
| J999 | Not reported | 161 | 100 | Solar | Withdrawn |
| R5072 | Replacing 100 MW of Solar with Nuclear; Duane Arnold | n/r | 100 | Nuclear | Active |
| J1359 | Not reported | 69 | 95 | Gas | Active |
| R1042 | Replacing 50 MW of solar generation with BESS; Duane Arnold | 161 | 64 | Hybrid | Withdrawn |
| R5070 | Replacing 50 MW of Solar with Nuclear; Duane Arnold | n/r | 64 | Nuclear | Active |
| J1889 | Not reported | n/r | 60 | Solar | Active |
| R1007 | Replace 60 MW of ALTW.FPL_DAEC Unit with Battery; Duane Arnold | 161 | 60 | Hybrid | Withdrawn |
| J1285 | Not reported | 345 | 50 | Battery | Withdrawn |
| J504 | Not reported | 161 | 50 | Solar | Active |
| G726 | Not reported | n/r | 30 | Nuclear | Operational |
| G230 | Not reported | n/r | 2 | Other | Operational |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.