Substation Scout

MISO request J1889

MISO queue ID J1889

Queue request J1889 was listed in the MISO interconnection queue at the end of 2025 as a 60 MW solar project in Linn County, IA, according to Berkeley Lab’s queue data file. The filing names Mount Vernon as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2025.

Queue IDJ1889
Project nameNot reported
Status (as published)Active
SubstationMount Vernon
Point of interconnectionMount Vernon
CountyLinn
StateIA
VoltageNot reported
Capacity60 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2025-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Linn, IA: 26 requests in the MISO queue, 16 active totaling 3,679.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC MIDWEST
ClusterDPP-2021 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 3; Post GIA Status: Not Started
Queue date2021-08-04

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.